About the project
ITPS are a specialist IT managed solutions provider with data centres located across the North of England. As the only North East stage two-certified supplier for NHS Digital and a Microsoft Azure partner, demand for ITPS’ services are seeing continued growth.
As ITPS’ technology partner Keysource had delivered the initial design and build of their flagship facility in 2014. With the need for increased capacity as well specific security and high performance customer requirements, Keysource were engaged to deliver the update of the facilities second hall.
The 30,000 sq ft site has a total 1.6MW capacity, with 900kW partitioned into different data halls for specific clients. The upgrade added an additional 300kW, leaving ITPS with further spare capacity to expand.
Keysource completed the upgrade to the second hall at the 8,500 sq ft data centre in just 12 weeks with no disruption to the existing environment. The expansion has been specifically fitted out to suit one of ITPS’ largest clients’ high performance and security needs – including new high security caging.